Ryse E-5 wind turbine at an Enagás gas distribution plant in Spain
Case studies

Pipelines, Enagás

E-5 and E-3 turbines with battery storage power Enagás pipeline control, monitoring and cathodic protection off-grid in Spain.

Ryse E-5 wind turbine at an Enagás gas distribution plant in Spain
Case studies

Pipelines, Enagás

E-5 and E-3 turbines with battery storage power Enagás pipeline control, monitoring and cathodic protection off-grid in Spain.

LOCATION
Spain
SYSTEM TYPE
Off-grid wind and storage
WIND CAPACITY
E-5 and E-3
APPLICATION
Gas pipeline control and cathodic protection

Project Overview

Enagás relies on Ryse wind power at two off-grid pipeline sites in Spain.

At one distribution plant, an E-5 wind turbine with a passive variable-pitch system generates more than 8 kWh per day at an average wind speed of 3.5 m/s at 12 m height. With a battery bank, it powers the automatic controls and monitoring of the pipeline, as well as lighting and the station’s own needs.

At a cathodic protection station on the Castelnou to Tivissa gas pipeline, an E-3 turbine generates more than 7 kWh per day at an average wind speed of 4.5 m/s at 12 m. With a 360 W inverter and a 24 V, 1,200 Ah battery bank, the installation provides 7 days of autonomy without wind and carries full responsibility for the station’s electricity supply.

Products in this project: E-5 5 kW wind turbine and E-3 3 kW wind turbine.

Frequently asked questions

Why does a cathodic protection station need continuous power?

Cathodic protection applies a small electrical current to a pipeline to prevent corrosion, so the supply cannot stop. At the Castelnou to Tivissa pipeline, an E-3 turbine and batteries carry full responsibility for the station’s electricity.

How long can the system run without wind?

The cathodic protection installation is designed for 7 days of autonomy without wind, using a 24 V, 1,200 Ah battery bank.

How much energy do the turbines produce?

The E-5 at the distribution plant generates more than 8 kWh a day at an average wind speed of 3.5 m/s. The E-3 generates more than 7 kWh a day at 4.5 m/s. Both are measured at 12 m height.

Can small wind power a pipeline without a grid connection?

Yes. Both Enagás sites are off-grid, with wind turbines and batteries supplying control, monitoring and cathodic protection loads.

How can Ryse help with a similar oil and gas site?

Ryse designs, supplies and installs hybrid wind, solar, battery and microturbine systems for remote oil and gas loads, and provides maintenance and monitoring. See oil and gas power systems or talk to our team.

Project snapshots

See how it came together in real life.

What our partners say

Trusted by Industry Leaders Around the World

We’ve worked with telecom giants, governments and infrastructure providers to deliver long-term energy solutions where they matter most.

Over 180,000 Ryse systems installed worldwide

Ready to power your project with Ryse?

Whether you're just getting started or ready to build, our team is here to help.

Over 180,000 Ryse systems installed worldwide

Ready to power your project with Ryse?

Whether you're just getting started or ready to build, our team is here to help.